The Del Mar City Council approved agreements with Gangi Development on Tuesday, Nov. 10, to begin predevelopment work on affordable housing at a tiny city-owned lot on 10th Street.
The council's vote authorized an Exclusive Negotiating Rights Agreement and a Predevelopment Funding Agreement with Gangi Development, according to a city announcement published Nov. 12. The agreements set a negotiating period and timeline for predevelopment studies, plans, community outreach, environmental review and permits.
The approval does not greenlight a specific building design or development proposal.
The vacant lot sits on the southwest corner of the Civic Center complex and measures just 0.10 acres, or 4,356 square feet. Del Mar's state-certified Housing Element requires the city to develop at least four units of affordable housing there to help meet an obligation for 113 lower-income units.
A February 2026 agenda report from City Manager Ashley Jones described the city's goal of building up to eight small units for lower-income households on the lot. A 2022 feasibility study considered a two-story building with four two-bedroom units averaging 718 square feet, according to the agenda report. That same structure could hold eight units if designed as studios or one-bedrooms closer to 500 square feet.
The Housing Element requires the city to issue building permits for at least seven lower-income units by 2027, the agenda report stated. Pursuing eight units on 10th Street could help the city reach that milestone.
The council had originally planned to take up the Gangi Development agreements on Oct. 20 but postponed the item to Nov. 10. City staff recommended the delay after communications with the state Department of Housing and Community Development to ensure Housing Element compliance.
As of a May 19 city staff presentation, Del Mar had achieved 77% of its overall Housing Element target of 175 dwelling units through 2029, reaching 135 units. Most of those units, however, fell in the moderate- and above-moderate-income categories, according to a city update.
Development details such as the total number of units, parking and design will go through community outreach and review by the Design Review Board and Planning Commission before returning to the City Council for final approval.