Del Mar has installed emergency pumps at flood-prone spots and finished training exercises with first responders as the city braces for El Niño storms forecast for this winter.

City staff delivered a third update to the City Council on Tuesday, Nov. 10, covering pump deployments, a multi-agency flood drill and the status of the San Dieguito Lagoon inlet.

Pumps and equipment

Earlier in November, the city installed a rented pump at a drainage ditch west of the train tracks between 21st and 28th streets, according to the city's update. The pump can move 1,500 gallons per minute during high tides.

Backup pumps were added at stormwater stations on 20th, 27th and 29th streets in case existing equipment fails or is overwhelmed. The Fire Department received an 80-gallon-per-minute pump for a low-lying stretch of Ocean Front between 18th and 19th streets. That equipment joins generators, a vacuum truck and fire engines already on hand.

Flood drill in Beach Colony

In October, a training exercise simulated a flood in the Beach Colony neighborhood. Six city departments, the Sheriff's Office and SDG&E took part. The drill envisioned flooding from high surf, tides and rainfall that could not drain. It tested activation levels for the Emergency Operations Center and evacuation procedures. The Red Cross identified shelter sites.

Del Mar lifeguards and firefighters also completed swift-water rescue training, the update stated.

Representatives from six city departments continue to meet weekly on storm preparations.

Beach berms and lagoon inlet

On the beach, Del Mar has hired a contractor with specialized equipment to build berms at street ends and public access points to protect infrastructure and reduce coastal flooding.

At the San Dieguito Lagoon, staff told the council that Southern California Edison reported no dredging is needed this year. Edison said the volume of water flowing through the inlet is adequate. The utility manages the lagoon inlet under its own permit as part of the San Dieguito Wetlands Restoration Program. Edison officials told the city they will continue to monitor the inlet and will respond if it closes.

That marks a shift from September, when concerns about sand buildup prompted a local emergency declaration. The City Council adopted the declaration Sept. 22, asking the Army Corps of Engineers to amend permits to allow removal of up to 50,000 cubic yards of sand per dredge event, well above the existing 16,000-cubic-yard limit. Gov. Gavin Newsom's Sept. 21 statewide emergency proclamation called for expedited permit reviews for El Niño preparations.

Assistant City Manager Clem Brown presented earlier El Niño updates to the council, according to city agenda records.